top of page

Legal Review and Analysis of A A Estates Private Limited & Anr vs Kher Nagar Sukhsadan Co op Housing Society Ltd & Ors 2025 INSC 1366

Case Synopsis:

A A Estates Private Limited & Anr. vs. Kher Nagar Sukhsadan Co-op. Housing Society Ltd. & Ors. (2025 INSC 1366)

Synopsis: The Supreme Court delineated the boundaries of the IBC's moratorium, ruling that it does not protect development rights under an agreement that was validly terminated for the corporate debtor's non-performance before the initiation of insolvency proceedings. Emphasizing that the IBC is not a refuge for defaulting parties, the Court held that such extinguished rights do not constitute "assets," thereby allowing a housing society to proceed with a new developer to secure the fundamental right to housing of its residents. The Court also affirmed the High Court's writ jurisdiction to direct statutory authorities in this context.


1. Heading of the Judgment

Case Title: A A Estates Private Limited & Anr. vs. Kher Nagar Sukhsadan Co-op. Housing Society Ltd. & Ors
Citation: 2025 INSC 1366
Court: Supreme Court of India
Bench: Justice J.B. Pardiwala and Justice R. Mahadevan
Jurisdiction: Civil Appellate Jurisdiction (Arising out of Special Leave Petition (C) No. 10758 of 2025)


2. Related Laws and Sections

This judgment primarily interprets the interplay between contractual rights, specifically in real estate development agreements, and the protections offered under the Insolvency and Bankruptcy Code, 2016 (IBC). The key legal provisions discussed are:

  • Insolvency and Bankruptcy Code, 2016 (IBC):
    Section 3(27): Definition of "Property".
    Section 14: Moratorium on the initiation and continuation of legal proceedings and the transfer of assets once the Corporate Insolvency Resolution Process (CIRP) commences.
    Section 60(5)(c): Jurisdiction of the National Company Law Tribunal (NCLT) to adjudicate questions of law or facts arising from the insolvency resolution process.

  • Indian Contract Act, 1872: Principles governing the valid termination of contracts for breach.

  • Constitution of India, Article 226: Power of High Courts to issue certain writs.


3. Basic Judgment Details

A. Facts of the Case

  • The Parties: Appellant No. 1, A A Estates Pvt. Ltd., is a corporate debtor undergoing CIRP. Appellant No. 2 is its Resolution Professional. Respondent No. 1 is a cooperative housing society whose building was in a dilapidated condition.

  • The Original Agreement: In 2005, the Society entered into a Development Agreement with A A Estates for redevelopment. A Supplementary Agreement was executed in 2014, extending the timeline.

  • Alleged Defaults: The Society alleged that A A Estates failed to complete the project, pay transit rents consistently, and secure vacant possession from all members, leading to inordinate delays spanning nearly two decades.

  • Termination and New Developer: The Society terminated the agreement in 2019 (and reiterated in 2021) and subsequently appointed a new developer, Respondent No. 8, in 2023.

  • Initiation of CIRP: A A Estates entered CIRP in December 2022. The Resolution Professional objected to the Society's actions, claiming they violated the statutory moratorium under Section 14 of the IBC.

  • The Writ Petition: The Society filed a writ petition before the Bombay High Court, seeking a direction to statutory authorities to grant redevelopment permissions to the new developer. The High Court allowed the petition.

  • The Appeal: A A Estates and the Resolution Professional appealed to the Supreme Court against the High Court's order.


B. Issues for Determination

The Supreme Court framed the following four issues:

  1. Whether the termination of the Development Agreement by the Society prior to the initiation of the second CIRP was valid and effective in law?

  2. Whether the Development Agreement constituted an "asset" or "property" of the corporate debtor, attracting the protection of the moratorium under Section 14 of the IBC?

  3. Whether the High Court was justified in allowing the writ petition and directing statutory authorities to grant approvals to the new developer?

  4. Whether the proceedings before the High Court were vitiated by a violation of the principles of natural justice?


C. Ratio Decidendi (The Court's Reasoning)

The Court's reasoning on each issue was as follows:


On Issue No. 1 (Validity of Termination):
The Supreme Court upheld the termination as valid. It reasoned that the developer's persistent failure to perform its core obligations—commencing construction and paying transit rents—constituted a material breach. The termination was based on grounds unrelated to the corporate debtor's insolvency, such as chronic default, which occurred well before the CIRP was initiated. The Court relied on precedents like Gujarat Urja Vikas Nigam Ltd. v. Amit Gupta (2021) and Tata Consultancy Services Ltd. v. SK Wheels Pvt. Ltd. (2022), which hold that the NCLT cannot interfere with a contractual termination that is based on legitimate defaults and not merely triggered by the insolvency itself.


On Issue No. 2 (Development Rights as 'Asset' under IBC):
This was the core legal question. The Court held that the development rights under the terminated agreement did not constitute an "asset" or "property" of the corporate debtor protected by the Section 14 moratorium. The Court made a crucial distinction:

  • The Development Agreement granted only a licence to carry out work, not a proprietary or possessory interest in the land. The Society remained the absolute owner and in physical possession throughout.

  • Since the agreement was validly terminated before the CIRP commenced, no subsisting, enforceable right existed in favour of the corporate debtor on the "insolvency commencement date."

  • The Court distinguished the case from Victory Iron Works Ltd. v. Jitendra Lohia (2023), noting that in that case, the corporate debtor had a demonstrable bundle of rights akin to ownership, which was absent here. The mere right to sue for damages for wrongful termination is an unsecured claim, not a protected asset under Section 14.


On Issue No. 3 (Justification of High Court's Writ Jurisdiction):
The Supreme Court affirmed the High Court's exercise of power under Article 226. It held that the writ petition was not an adjudication of a private contractual dispute but a challenge to the inaction of statutory authorities (like the municipal corporation and MHADA) who were withholding permissions due to the CIRP. Directing these authorities to perform their public law duty to process applications does not trench upon the NCLT's domain under the IBC. The Court cited Embassy Property Developments Pvt. Ltd. v. State of Karnataka (2020) to reiterate that the constitutional writ jurisdiction of High Courts is not ousted by the IBC.


On Issue No. 4 (Violation of Natural Justice):
The Court rejected this argument, finding that the appellants were duly served, represented by counsel, and had ample opportunity to present their case before the High Court. Their failure to file a reply or seek an adjournment was their own choice and did not amount to a denial of a fair hearing. No specific prejudice was demonstrated.


4. Core Principle of the Judgment

Title: The Sanctity of Contractual Termination vs. Insolvency Moratorium: Protecting Public Welfare over Defunct Rights

The central legal issue addressed by the Supreme Court was the precise interplay between the IBC's moratorium, designed to protect the corporate debtor's estate, and the rights of a principal to terminate a contract with a defaulting developer for non-performance.


The Main Issue and the Court's Resolution

The core conflict was whether a corporate debtor, which has demonstrably failed to perform its contractual obligations for years, can use the shield of the Section 14 moratorium to prevent a housing society from appointing a new developer and proceeding with a vital redevelopment project, especially after the original agreement has been terminated.

The Supreme Court delivered a clear and principled resolution:

  • IBC is Not a Shield for Non-Performance: The moratorium under Section 14 of the IBC is intended to preserve the existing, subsisting estate of the corporate debtor to facilitate resolution. It is not a sanctuary for defunct rights or a tool to resurrect contracts that were validly terminated due to the debtor's own defaults prior to the insolvency.

  • Subsistence is Key: For a development agreement to be considered an "asset," it must be legally alive and enforceable on the date of the CIRP's commencement. A right that has been extinguished by a valid, non-insolvency-related termination ceases to be part of the estate.

  • Primacy of Public Welfare: In matters involving redevelopment of dilapidated buildings, the rights of residents to safe and dignified shelter under Article 21 of the Constitution weigh heavily in the balance. The IBC cannot be used to perpetuate their hardship and indefinitely stall projects of public significance.

The judgment thus draws a bright line: the IBC protects viable assets for the benefit of the corporate debtor's revival, but it does not immunize a debtor from the consequences of its own pre-insolvency breaches or allow it to hold public welfare projects hostage.


5. Final Outcome and Supreme Court's Direction

The Supreme Court dismissed the appeal filed by A A Estates and its Resolution Professional. It upheld the judgment of the Bombay High Court. The key directions and findings were:

  • The termination of the Development Agreement with A A Estates was valid.

  • The said agreement did not form part of the corporate debtor's assets protected by the moratorium.

  • The High Court was correct in directing the statutory authorities to process the permissions for the new developer.

  • The appellants were at liberty to pursue their claim for the amounts spent on the project as an unsecured claim in the insolvency process.


MCQs Based on the Judgment


1. As per the Supreme Court's judgment in A A Estates vs. Kher Nagar Sukhsadan CHS (2025 INSC 1366), a development agreement will be considered an "asset" of the corporate debtor under Section 14 of the IBC only if?
(a) It was signed by the corporate debtor, regardless of performance.
(b) It confers a subsisting and enforceable right on the date of commencement of the CIRP.
(c) It involves a project for the redevelopment of a housing society.
(d) The corporate debtor has made some financial investment in the project.


2. In the aforementioned case, the Supreme Court held that the High Court's exercise of writ jurisdiction under Article 226 was justified because?
(a) The High Court has superior jurisdiction over the NCLT in all matters.
(b) The petition sought to compel statutory authorities to perform their public duty, which is within the realm of public law.
(c) The IBC does not apply to disputes involving cooperative housing societies.
(d) The corporate debtor had consented to the High Court's intervention.

Blog Posts

  • Picture2
  • Telegram
  • Instagram
  • LinkedIn
  • YouTube

Copyright © 2025 Lawcurb.in

bottom of page