top of page

Legal Review and Analysis of Regenta Hotels Private Limited vs Ms Hotel Grand Centre Point & Others 2026 INSC 32

I. Basic Information & Synopsis

Case Title: Regenta Hotels Private Limited vs. M/s Hotel Grand Centre Point & Others

Court: Supreme Court of India

Jurisdiction: Civil Appellate Jurisdiction

Citation: 2026 INSC 32

Coram: Justices Dipankar Datta & Augustine George Masih (Bench of Two Judges)

Date of Judgment: January 07, 2026

Synopsis: This judgment clarifies the pivotal issue of when arbitral proceedings are deemed to have "commenced" under the Arbitration and Conciliation Act, 1996, for the purpose of complying with the 90-day timeline stipulated under Section 9(2) of the Act to prevent the automatic vacation of an interim injunction. The Supreme Court authoritatively held that commencement is governed solely by Section 21 of the Act, i.e., the date the respondent receives the notice invoking arbitration, and not by the date of filing a petition for the appointment of an arbitrator under Section 11. The Court set aside the High Court's order which had vacated an interim injunction on the erroneous ground that arbitration commenced only upon the filing of a Section 11 petition, which was done after 90 days.


II. Legal Framework & Precedents

  • Primary Legislation:
    The Arbitration and Conciliation Act, 1996 (the "Act").
    Relevant Sections:
    Section 9: Grants courts the power to pass interim measures before, during, or after arbitral proceedings. Sub-section (2) mandates that if an interim order is passed before the commencement of arbitral proceedings, such proceedings must be commenced within 90 days, extendable by the court.
    Section 21: Defines "Commencement of arbitral proceedings." It states that unless otherwise agreed, proceedings commence on the date a request to refer the dispute to arbitration is received by the respondent.
    Section 43(2): For the purposes of limitation, arbitration is deemed to have commenced on the date referred to in Section 21.

  • Subsidiary Rules: Rule 9(4) of the Arbitration (Proceedings Before the Courts) Rules, 2001 ("2001 Rules"), framed under Section 82 of the Act. It states that if arbitral proceedings are not initiated within three months from the date of a Section 9 application, any interim order stands vacated automatically.

  • Key Precedents Relied Upon:
    Sundaram Finance Ltd. v. NEPC India Ltd. (1999): Established that courts have power under Section 9 even before arbitral proceedings commence.
    Milkfood Ltd. v. GMC Ice Cream (P) Ltd. (2004): Held that Section 21, modeled on UNCITRAL Model Law, is determinative of commencement and is not solely for limitation purposes.
    Geo Miller and Company Pvt. Ltd. v. Rajasthan Vidyut Utpadan Nigam Ltd. (2020): Reaffirmed that the date of commencement is the date of receipt of the arbitration notice, independent of subsequent procedural steps.
    Arif Azim Company Ltd. v. Aptech Ltd. (2024): Consolidated the law, stating that a valid Section 21 notice completes commencement for all legal purposes, including the efficacy of pre-arbitral measures.


III. Relevant Facts of the Case

  1. Parties & Agreement: Appellant, Regenta Hotels, entered into a Franchise Agreement (23.03.2019) with Respondent No.1, a partnership firm (Hotel Grand Centre Point), to operate a hotel in Srinagar.

  2. Dispute: Respondent No.2 (a partner) allegedly started interfering with hotel operations. The Appellant filed a Section 9 application before the Trial Court seeking an injunction against Respondent No.2.

  3. Interim Relief & Notice: The Trial Court granted an ad-interim injunction on 17.02.2024. The Appellant issued an arbitration notice under Section 21 to all respondents on 11.04.2024.

  4. Response & Section 11 Petition: Respondent No.2 replied on 23.04.2024, refusing arbitration and claiming he was not a signatory. Consequently, the Appellant filed a petition under Section 11 for arbitrator appointment on 28.06.2024.

  5. Lower Courts' Decisions:
    Trial Court (01.10.2024): Dismissed the injunction application, doubting the existence of a prima facie case against Respondent No.2.
    High Court (Impugned Judgment, 14.11.2024): Upheld dismissal but on different grounds. It held that arbitral proceedings had not commenced within 90 days of the interim order (17.02.2024). The Court reasoned that commencement required a request for arbitration to be "received" by the respondent in a manner constituting a valid reference. It treated the filing of the Section 11 petition (28.06.2024) as the commencement date, which was beyond 90 days, leading to the automatic vacation of the injunction under Rule 9(4).


IV. Issues Before the Supreme Court

The core legal issue was
Whether the High Court was correct in holding that the Appellant failed to commence arbitral proceedings within 90 days of the ad-interim injunction order dated 17.02.2024, as mandated by Section 9(2) of the Act read with Rule 9(4) of the 2001 Rules, by erroneously treating the date of filing the Section 11 petition as the date of "commencement"?


V. Ratio Decidendi & Judgment of the Court

The Supreme Court allowed the appeal and set aside the orders of the High Court and the Trial Court. The ratio decidendi (the reason for the decision) is as follows:

The commencement of arbitral proceedings is a statutory event defined exclusively under Section 21 of the Arbitration and Conciliation Act, 1996. For the purpose of complying with the 90-day timeline under Section 9(2) of the Act, arbitral proceedings are deemed to have commenced on the date the respondent receives a request to refer the dispute to arbitration, as per Section 21. This date is not contingent upon, and cannot be substituted by, the date of filing a judicial application under Section 11 of the Act for appointment of an arbitrator.


VI. Legal Framework Established & Clarified

  1. Harmonious Construction of "Initiated" and "Commenced": The Court resolved the apparent discord between Section 9(2) ("commenced") and Rule 9(4) ("initiated"). It held that in the context of the Act and the Rules framed thereunder, "initiated" in Rule 9(4) must be read as synonymous with "commenced" under Section 21. Any other interpretation would render Section 9(2) otiose and defeat the statutory scheme.

  2. Section 21 is of Universal Application: The Court rejected the contention that Section 21 is only for calculating limitation under Section 43(2). It affirmed that Section 21 provides the singular, definitive point of commencement for all purposes under the Act, unless a provision explicitly states otherwise.

  3. Delinkage from Judicial Process: The Court emphasized the legislative intent, inspired by the UNCITRAL Model Law, to delink the commencement of arbitration from any judicial proceeding. The trigger is the party's act of invoking arbitration via notice, not the court's intervention under Section 11.

  4. Purpose of Section 9(2) Safeguard: The 90-day rule is a safeguard against abuse of interim relief, ensuring a party does not indefinitely enjoy court-ordered protection without moving towards arbitration. This purpose is fulfilled once a valid Section 21 notice is served, as the party has taken the essential step to submit to arbitration.


VII. Court's Analysis & Examination

The Supreme Court's analysis proceeded systematically:

  1. Review of Precedents: The Court extensively reviewed its consistent line of judgments from Sundaram Finance to Arif Azim, affirming the primacy of Section 21 in determining commencement.

  2. Statutory Interpretation: It performed a plain reading of Sections 9(2), 21, and 43(2), concluding that the Act provides no other benchmark for commencement.

  3. Logical & Teleological Reasoning: The Court reasoned that if the date of a Section 11 petition were treated as the commencement date, it would create an absurd and impractical scenario. A party who serves a Section 21 notice and is actively negotiating an arbitrator with a cooperative respondent could still lose its interim protection simply because it hasn't yet filed a Section 11 petition. This would force unnecessary litigation and undermine party autonomy.

  4. Application to Facts: Applying this settled law, the Court found:
    The ad-interim order was passed on 17.02.2024.
    The 90-day period ended on 17.05.2024.
    The Appellant issued the arbitration notice on 11.04.2024, which was received by the respondent (evidenced by his reply on 23.04.2024).
    Therefore, arbitral proceedings commenced on 11.04.2024 (or at the latest 23.04.2024), which was well within the 90-day window.
    The High Court erred in using the Section 11 filing date (28.06.2024) as the commencement date.


VIII. Critical Analysis & Final Outcome

Critical Analysis
This judgment is a robust affirmation of pro-arbitration principles. It provides crucial clarity and prevents a technical trap for parties seeking interim protection. By cementing the primacy of the Section 21 notice, the Court:

  • Upholds Party Autonomy: Encourages parties to follow agreed appointment procedures before rushing to court.

  • Prevents Injustice: Protects a party's interim relief from lapsing due to procedural delays in court appointments, especially when the other party is non-cooperative.

  • Promotes Efficiency: Aligns Indian arbitration law with international best practices (UNCITRAL Model Law) by focusing on the parties' actions rather than court timelines.

  • Critique: A potential consideration is that a recalcitrant respondent could, upon receiving a Section 21 notice, simply remain silent (not reply), potentially creating ambiguity over the "date of receipt." However, the Court's reliance on the date the notice was sent (or the date a reply evidences receipt) mitigates this concern.


Final Outcome

  1. The Impugned Judgment of the High Court was set aside.

  2. The Trial Court's order vacating the injunction was also set aside.

  3. The ad-interim injunction order dated 17.02.2024 was restored.

  4. The Supreme Court directed the High Court to expeditiously decide the pending Section 11 petition for arbitrator appointment.

  5. The connected Contempt Petition was disposed of.


IX. Multiple Choice Questions 


1. As per the Supreme Court's judgment in Regenta Hotels, for the purpose of Section 9(2) of the Arbitration Act, arbitral proceedings are deemed to have commenced?
a) On the date the arbitral tribunal is formally constituted.
b) On the date of filing an application under Section 11 for appointment of arbitrator.
c) On the date the respondent receives a request for arbitration under Section 21.
d) On the date the court passes an interim order under Section 9.


2. The Supreme Court interpreted the term "initiated" used in Rule 9(4) of the 2001 Rules to mean?
a) The first communication expressing a desire to arbitrate.
b) The filing of a statement of claim before the arbitral tribunal.
c) The same as "commenced" under Section 21 of the Act.
d) The commencement of arguments in the arbitral hearing.


3. Which of the following was NOT cited as a rationale for the Supreme Court's decision?
a) To prevent parties from abusing interim measures without moving to arbitration.
b) To align Indian law with the UNCITRAL Model Law framework.
c) To reduce the caseload of courts under Section 11 petitions.
d) To uphold the statutory scheme which delinks commencement from judicial proceedings.


4. In the present case, the Supreme Court restored the interim injunction because?
a) The Appellant had filed the Section 11 petition within 90 days.
b) The Appellant had issued the Section 21 arbitration notice within 90 days of the interim order.
c) The Respondent No.2 was found to be a signatory to the franchise agreement.
d) The Trial Court had erred in its factual findings regarding partnership consent.

Blog Posts

  • Picture2
  • Telegram
  • Instagram
  • LinkedIn
  • YouTube

Copyright © 2026 Lawcurb.in

bottom of page