top of page

Legal Review and Analysis of The State of Jharkhand vs The Indian Builders Jamshedpur 2025 INSC 1388

Case Synopsis

The State of Jharkhand vs. The Indian Builders Jamshedpur (2025 INSC 1388)

Supreme Court Questions Precedent on Arbitration; Refers Bharat Drilling to Larger Bench to Clarify Binding Nature of Contractual Claim Prohibitions. The judgment underscores that an arbitrator cannot adjudicate claims expressly barred by the contract, reaffirming party autonomy as the cornerstone of arbitration. It seeks to correct the erroneous application of a precedent concerning interest to substantive claim prohibitions.


1. Heading of the Judgment

Case Name: The State of Jharkhand vs. The Indian Builders Jamshedpur
Citation: 2025 INSC 1388
Court: Supreme Court of India
Bench: Honourable Mr. Justice Pamidighantam Sri Narasimha and Honourable Mr. Justice Atul S. Chandurkar
Date of Judgment: December 5, 2025


2. Related Laws and Sections

  • Arbitration and Conciliation Act, 1996: Section 31(7) (Form and contents of arbitral award — Interest), Section 34 (Application for setting aside arbitral award), Section 37 (Appealable orders).

  • Contractual Clauses: Specifically, "excepted" or "prohibited claim" clauses within a government contract, which in this case were:
    Clause 4.20.2: "No claim for idle labour, idle machinery, etc. on any account will be entertained…"
    Clause 4.20.4: "No claim shall be entertained for business loss or any such loss."

  • Interpretative Precedents: Bharat Drilling & Foundation Treatment Pvt. Ltd. v. State of Jharkhand and Ors. (2009) 16 SCC 705; Board of Trustees For The Port of Calcutta v. Engineers-De-Space-Age (1996) 1 SCC 516; Pam Developments Private Limited v. State of West Bengal (2024) 10 SCC 715; Central Organisation for Railway Electrification (CORE), 2024 INSC 857.


3. Judgment Details

A. Facts of the Case

  1. The State of Jharkhand (Appellant) entered into a contract with The Indian Builders Jamshedpur (Respondent) which contained specific clauses prohibiting certain types of claims (Clauses 4.20.2 and 4.20.4).

  2. A dispute arose, and the Arbitral Tribunal, in its award dated April 19, 2007, allowed several claims filed by the Respondent, including Claim Nos. 3 (underutilised overheads), 4 (loss due to underutilised tools, plants and machinery), and 6 (loss of profit).

  3. The State filed objections under Section 34 of the Arbitration Act before the Civil Court. The Civil Court set aside the award on Claim Nos. 3, 4, and 6, holding they were expressly prohibited under the contract.

  4. The Respondent appealed to the Jharkhand High Court under Section 37. The High Court, relying solely on the Supreme Court's decision in Bharat Drilling (supra), allowed the appeal and restored the arbitral award on the prohibited claims without analyzing the contractual clauses.

  5. The State, aggrieved by the High Court's judgment, appealed to the Supreme Court.


B. Issues Before the Supreme Court

  1. Whether the High Court was correct in restoring the arbitral award on claims expressly prohibited by the contract, based solely on the precedent of Bharat Drilling (supra)?

  2. Whether the decision in Bharat Drilling (supra) correctly states the law that a contractual bar against certain claims applies only to the employer and not to the Arbitral Tribunal?


C. Ratio Decidendi (Court’s Reasoning)

I. Critical Examination of the Bharat Drilling Precedent:
The Supreme Court found that the High Court had committed a serious error by applying Bharat Drilling (supra) mechanically, without examining the specific prohibitory clauses in the contract. Upon review, the Supreme Court noted that Bharat Drilling itself had not conducted a detailed analysis of such contractual clauses. It had merely referenced Port of Calcutta (supra), a case dealing with the arbitrator's power to award interest, which is governed by a distinct statutory provision (Section 31(7) of the Arbitration Act).


II. Primacy of Party Autonomy and Contractual Terms:
The Supreme Court reaffirmed the fundamental principle of party autonomy as the "brooding and guiding spirit" of arbitration. Citing its recent decision in CORE (supra), the Court emphasized that an Arbitral Tribunal is bound by the procedures and limitations agreed upon by the parties in their contract. Prohibitory clauses that crystallize the informed choices of the parties must be respected.


III. Distinction Between Prohibited Claims and Award of Interest:
The Court drew a clear legal distinction:

  • Prohibited Claims (e.g., for idle machinery, business loss): These are substantive rights waived or excluded by the contract. An arbitrator cannot award on a claim the parties have agreed is not entertainable.

  • Award of Interest: This power is derived from Section 31(7) of the Arbitration Act. The jurisprudence around interest (as in Port of Calcutta) involves interpreting whether a contractual clause specifically bars the arbitrator from granting interest. This is a separate and distinct issue from whether a substantive claim itself is permissible.


IV. Conflict with Recent Jurisprudence and Need for Clarity:
The Supreme Court observed that the approach in Bharat Drilling—suggesting a contractual bar applies only to the employer and not the tribunal—was inconsistent with later, well-reasoned decisions like Pam Developments (supra). In Pam Developments, the Court held it is the duty of the arbitrator (and reviewing courts) to examine the contract, and awarding amounts on claims expressly prohibited renders the award unsustainable.


4. Core Principle of the Judgment

The Supreme Court addressed the core issue of the binding nature of "excepted" or "prohibited claim" clauses in arbitration agreements and the incorrect application of a precedent that conflated distinct legal principles.


Judicial Analysis on the Binding Force of Contractual Prohibitions in Arbitration:
The core of this judgment is a decisive reaffirmation of the supremacy of the contract in arbitration proceedings. The Supreme Court identified and sought to correct a developing error in arbitration law: the misuse of the Bharat Drilling decision to bypass clear contractual prohibitions. The Court meticulously delineated the law, establishing that:

  1. An Arbitral Tribunal is not a super-contracting authority. Its jurisdiction and the scope of claims it can adjudicate are defined by the agreement between the parties. Where the parties have unequivocally agreed that certain claims (like those for idle machinery or business loss) "shall not be entertained," the tribunal is bound by that agreement.

  2. Precedents must be applied in their correct context. The Court highlighted the legal misstep in using Bharat Drilling, which concerned interest, to justify ignoring prohibitions on substantive claims. This conflation was creating uncertainty in government contracting.

  3. The duty to examine the contract is paramount. Both arbitrators and courts, at every stage (Sections 34 and 37), must examine whether a claim falls within a prohibited category as per the contract's terms. Failure to do so is a jurisdictional error.

By referring Bharat Drilling to a larger bench for reconsideration, the Supreme Court signaled the need for an authoritative pronouncement to settle the law, ensure consistency, and uphold the sanctity of contractual terms in the arbitral process.


5. Final Outcome and Directions

The Supreme Court did not finally decide the merits of the appeal between the parties. Instead, it took a seminal step to clarify the law.

  • The Court expressed a prima facie opinion that the High Court's judgment, based solely on Bharat Drilling, was erroneous.

  • The Court found the ratio in Bharat Drilling to be in need of reconsideration as it created uncertainty regarding the interpretation of prohibitory clauses in contracts.

  • Consequently, the Supreme Court referred the matter of reconsidering the legal principle in Bharat Drilling & Foundation Treatment Pvt. Ltd. v. State of Jharkhand to a larger bench.

  • The Registry was directed to place the judgment before the Hon’ble Chief Justice for appropriate orders to constitute a larger bench.


6. MCQ Questions Based on the Judgment


Question 1: In State of Jharkhand vs. Indian Builders Jamshedpur (2025 INSC 1388), why did the Supreme Court refer the precedent in Bharat Drilling (supra) to a larger bench?
A. To increase the number of judges hearing the immediate dispute between the parties.
B. Because it found the precedent was being misapplied to override clear contractual prohibitions on claims, creating legal uncertainty.
C. To reduce the backlog of cases in the Supreme Court.
D. Because the respondent had filed a review petition.


Question 2: According to the Supreme Court in this judgment, what is the fundamental principle that governs the power of an Arbitral Tribunal regarding claims expressly prohibited by the contract?
A. The principle of equity and good conscience.
B. The principle of party autonomy and the binding nature of the contract.
C. The principle that all claims must be heard on merits.
D. The principle of stare decisis (binding precedent).

Blog Posts

  • Picture2
  • Telegram
  • Instagram
  • LinkedIn
  • YouTube

Copyright © 2025 Lawcurb.in

bottom of page