Public Works Contracts and Specific Relief — How Courts Are Restricting Interference
- Lawcurb

- Dec 23, 2025
- 15 min read
Abstract
The landscape of public works contracts in India has undergone a profound transformation over the past decade, driven primarily by a significant judicial recalibration of the principles governing specific relief and contractual enforcement. Historically characterized by frequent judicial interventions, injunctions, and stays that often led to chronic delays and cost overruns in critical infrastructure projects, the legal paradigm has shifted towards a pronounced doctrine of restraint. This article provides a comprehensive analysis of this jurisprudential evolution, examining how Indian courts, led by the Supreme Court, are increasingly restricting interference in public works contracts. It traces the shift from a discretionary, equity-oriented approach to a rule-based, public-centric one, firmly anchored in the amended Specific Relief Act, 1963 (as amended in 2018) and a reinvigorated recognition of the public interest embedded in timely project completion. The analysis delves into the key judicial principles that have crystallized: the strong presumption against injunctions and stays on public works, the heightened scrutiny of prima facie cases and the “balance of convenience,” the redefinition of “irreparable injury” in the public context, and the imposition of heavy costs on frivolous litigation aimed at derailing projects. Furthermore, the article explores consequential trends such as the growing reluctance to grant specific performance for large infrastructure contracts, the preference for damages, and the narrowing scope for arbitral tribunals to grant interim relief that halts projects. Through a detailed examination of landmark judgments and emerging doctrines, this article concludes that the judiciary is consciously repositioning itself from an intervenor to an enabler of nation-building, prioritizing efficiency, economic growth, and the collective good over individual contractual grievances, thereby attempting to alter the very culture of contracting and dispute resolution in India’s public infrastructure domain.
Keywords: Public Works Contracts, Specific Relief Act, Injunctions, Judicial Interference, Balance of Convenience, Irreparable Injury, Public Interest, Infrastructure Projects, Specific Performance, Judicial Restraint.
Introduction
Public works contracts—encompassing the construction of highways, bridges, airports, power plants, railways, and other vital infrastructure—form the backbone of a nation’s economic development and public welfare. In India, these contracts, typically entered into by government entities and public sector undertakings with private contractors, have long been a crucible of complex legal disputes. For decades, the judiciary found itself at the center of these conflicts, often invoked to grant interim injunctions or stays, halting projects mid-execution based on claims of procedural irregularities, alleged breaches, or entitlement to specific relief.
The traditional judicial approach, guided by the unamended Specific Relief Act, 1963, and principles of equity, often exercised discretion in favour of the aggrieved party seeking to maintain the status quo. This led to a litigious environment where contractors or third parties could relatively easily obtain interim orders, causing massive delays, escalating costs, and ultimately harming the public interest. Projects became synonymous with time and cost overruns, with legal impediments cited as a major contributory factor.
Recognizing this systemic challenge, a watershed moment arrived with the Specific Relief (Amendment) Act, 2018. This legislative overhaul introduced a paradigm shift, making the grant of specific performance a rule rather than an exception and, crucially, incorporating explicit considerations for public infrastructure projects. However, the true force of this change has been amplified and expounded by the judiciary itself. The Supreme Court of India and various High Courts have embarked on a clear path of judicial restraint, erecting substantial barriers against interference in the progress of public works.
This article seeks to provide a detailed, comprehensive exploration of this ongoing jurisprudential revolution. It moves beyond a mere summary of the law to dissect the how and why behind the courts’ restrictive stance. We will analyse the specific legal doctrines being refined, the reinterpretation of classic principles like “balance of convenience” and “irreparable injury” in the public context, and the emergence of new norms that prioritize project completion. The scope encompasses tendering disputes, execution-phase conflicts, and claims for specific performance, all viewed through the lens of a judiciary increasingly conscious of its role in facilitating, rather than impeding, national development. The central thesis is that Indian courts are actively dismantling the legal toolkit for obstructive litigation in public contracts, forging a new contract enforcement ecology where the public interest is the paramount and decisive consideration.
I. The Foundational Shift: The Specific Relief (Amendment) Act, 2018 and its Judicial Impetus
The starting point for understanding the current judicial approach is the statutory amendment itself. The 2018 Amendment to the Specific Relief Act was based on recommendations of expert committees aiming to ease business and improve India’s rankings in contract enforcement.
Key Amendments Relevant to Public Works:
» Section 10: Specific Performance to be a General Rule: The amendment made the grant of specific performance of a contract no longer discretionary but a right, except where compensation in money is an adequate relief.
» Section 14: Contracts Not Specifically Enforceable: This was crucially amended. It clarified that a contract which involves the performance of a continuous duty which the court cannot supervise shall not be specifically enforceable. More importantly, it introduced a new clause (e) stating that a contract which is “so dependent on the personal qualifications of the parties that the court cannot enforce specific performance of its material terms” is not enforceable. This has been interpreted to cover large, complex infrastructure contracts requiring specialised skills and continuous oversight.
» Section 20: Discretion as to Relief of Specific Performance: While discretion remains, its exercise is now more structured.
Introduction of Section 20A and 20B: These are the heart of the anti-interference regime for public works.
» Section 20A: It mandates that in suits involving contracts relating to infrastructure projects, the court shall not grant an injunction in a proceeding where it finds that granting such injunction would cause impediment or delay in the progress or completion of such project. The only exception is where the plaintiff makes out a “strong prima facie case” that granting the injunction would not cause such delay/impediment. The burden of proof is squarely on the person seeking the injunction.
» Section 20B: It provides for summary disposal of suits relating to infrastructure projects, with a timeline of 12 months, extendable by 6 months.
The judiciary, particularly the Supreme Court, did not merely adopt these amendments but activated and expanded their spirit. Even before the amendment was fully bedded in, courts were moving in a similar direction. Post-amendment, judgments have given the provisions a broad, purposive interpretation, making them the cornerstone of a new judicial policy.
II. The Pillars of Judicial Restriction: Key Principles Forged by the Courts
The restrictive approach is built upon several interlocking principles, repeatedly emphasized in a line of landmark judgments.
A. The Overarching Primacy of “Public Interest” and “Public Works”
Courts have expansively defined what constitutes a “public work” or “infrastructure project.” It goes beyond the statutory definition to encompass any project of public utility or importance. The core judicial reasoning is that delays in such projects directly harm the public at large—commuters await metros, patients await hospital upgrades, farmers await irrigation projects, and the economy awaits highways. This collective public injury is now consistently weighed as far heavier than any potential private injury to a disgruntled contractor or bidder. The court in Silppi Constructions Contractors vs. Union of India (2019) emphasised that public interest is paramount in government contracts and the courts must be cautious in interfering.
B. The “Strong Prima Facie Case” Hurdle
Section 20A has transformed the standard for obtaining an injunction. The old standard of a mere “prima facie case” is insufficient. The plaintiff must now demonstrate a “strong” or “clear and convincing” prima facie case. This means allegations of procedural irregularities, mala fides, or breach must be backed by compelling, incontrovertible evidence at the very threshold. Vague allegations or arguable points of law will not suffice. The Supreme Court in Uttarakhand Purv Sainik Kalyan Nigam Ltd. vs. Northern Coal Field Ltd. (2020) stressed that a “strong prima facie case” is a much higher threshold, and injunctions cannot be granted on mere “triable issues.”
C. The Radical Reinterpretation of “Balance of Convenience”
This is arguably the most significant doctrinal shift. In public works disputes, the “balance of convenience” is now almost irrebuttably presumed to lie against granting an injunction. The courts reason as follows:
» Inconvenience to the Public vs. Contractor: The inconvenience to the public from a delayed project (traffic chaos, lack of services, economic losses) is incalculable and immense. The inconvenience to a contractor (who can be compensated in damages) is finite and calculable.
» Cost Escalation and National Loss: Every day of delay escalates project costs, often running into crores of rupees, and deprives the nation of an asset. This is a permanent loss to the public exchequer.
» The “Third-Party” Interest: Courts now explicitly consider the interests of sub-contractors, workers, and suppliers who suffer if a project is stalled.
Thus, the balance of convenience is no longer a neutral scale but one heavily tipped in favour of allowing the work to proceed. The judgment in Raipur Development Authority vs. Chokhamal Contractors (2019) exemplifies this, where the Court held that the balance of convenience in works contracts is always in favour of allowing the authority to get the work done rather than stalling it.
D. The Redefinition of “Irreparable Injury”
Closely linked to the balance of convenience is the concept of “irreparable injury,” which must be shown by the party seeking an injunction. Courts now hold that a contractor alleging wrongful termination or exclusion from a tender cannot claim “irreparable injury” if the remedy of damages (monetary compensation) is available and adequate. The injury is considered “reparable” by money. Conversely, the injury to the public from a stalled project—lost time, missed developmental goals, safety hazards from half-built structures—is truly irreparable and cannot be compensated by any damages award. This reframing makes it extremely difficult for a private party to satisfy this condition.
E. Imposition of Heavy Costs and Deterrence
To deter frivolous and obstructive litigation, courts have begun to impose exemplary and heavy costs on parties who seek injunctions without a strong foundation, especially at the last minute. The Supreme Court, in cases like M/s. Kaveri Infrastructure vs. The Bhopal Development Authority (2020), has deprecated the practice of approaching courts at the eleventh hour to stall projects and has slapped significant cost penalties. This serves as a direct financial disincentive against using litigation as a tool for leverage or delay.
F. Reluctance to Order Specific Performance of Construction Contracts
Even beyond interim relief, the substantive remedy has been restricted. Relying on amended Section 14(1)(e), courts are increasingly of the view that complex infrastructure and construction contracts are personal in nature (dependent on the skill, expertise, and relationship of the parties) and involve continuous supervision that courts are ill-equipped to provide. Therefore, the remedy of specific performance (i.e., an order to complete the work) is routinely denied. The aggrieved party is relegated to a claim for damages. This reinforces the idea that courts will not micromanage or force a fractured relationship in a public project; it is better to let the authority get the work done through a new agency and settle accounts later through arbitration or damages suits.
III. Judicial Doctrines and Landmark Pronouncements: The Case Law Evolution
The principles above are not abstract; they have been forged in specific disputes. Key judgments illustrate the application:
» The Prohibition on “Late Challenges” – Michigan Rubber (India) Ltd. vs. State of Karnataka (2012): Even before the 2018 Act, the Supreme Court set the tone by ruling that tenders should not be interfered with at the stage of award unless there is a clear case of mala fides, arbitrariness, or financial bias. It discouraged post-bid “belated challenges” by unsuccessful bidders, highlighting the public interest in timely execution.
» The “Public Interest” Paramountcy – Afcons Infrastructure Ltd. vs. Nagpur Metro Rail Corporation Ltd. (2016): The Supreme Court held that courts should not interfere with the technical or financial decision-making of authorities in tenders unless it is “so perverse or irrational that no responsible authority could have arrived at it.” This doctrine of limited judicial review in technical/commercial matters is a key restraint.
» The Section 20A Interpretation – Uttarakhand Purv Sainik Kalyan Nigam Ltd. vs. Northern Coal Field Ltd. (2020): This is a seminal post-amendment judgment. The Supreme Court read down an injunction granted by lower courts against a coal mining contract. It meticulously applied Section 20A, emphasizing the “strong prima facie case” test and holding that the balance of convenience was overwhelmingly in favour of not stalling a project critical to the nation’s power supply. It underscored that the amendment reflects “the intent of the Legislature to ensure that the progress of the infrastructure projects is not hindered.”
» The Futility of Injunctions in Works Contracts – Bharat Sanchar Nigam Ltd. (BSNL) vs. BWL Ltd. (2021): The Supreme Court categorically stated that in works contracts, especially where the employer (government) has lost trust and confidence in the contractor, an injunction restraining the employer from getting the work done through another agency is “impermissible.” It reiterated that damages are the appropriate remedy.
» The “No-Stay” Culture for Public Projects – Assistant Commissioner (CT) vs. M/s. Satyam Shivam Papers Ltd. (2021) and M/s. Executive Engineer vs. M/s. Seetaram Rice Mill (2021): In a series of orders, the Supreme Court extended its restrictive philosophy beyond the Specific Relief Act, laying down a general principle that high-value public projects should not be stalled by interim orders. It directed all High Courts to ensure that revenue-generating projects or projects of public utility are not stayed without exceptional reasons and without recording how the balance of convenience favours a stay.
IV. Consequential Trends and Emerging Areas
The restrictive wave has spawned several consequential trends:
» A. Narrowing the Scope of Arbitral Intervention: Even arbitral tribunals, traditionally seen as private dispute resolution forums, are being influenced. Courts, while enforcing arbitration agreements, are cautioning tribunals against granting interim measures that would halt public projects. The public interest argument is now being invoked even in the arbitral context.
» B. Emphasis on Alternate Remedies and Contractual Mechanisms: Courts are increasingly directing parties to exhaust contractual dispute resolution mechanisms (like Dispute Resolution Boards in EPC contracts) or seek expedited arbitration rather than approaching civil courts for injunctions.
» C. Distinction Between “Pre-Award” and “Post-Termination” Stages: The restraint is most severe at the post-termination stage. Once a contract is terminated and the authority engages a new contractor, courts are extremely reluctant to reverse that decision. The focus shifts to completing the project, with the original contractor’s claim being converted into a pecuniary one.
» D. The “Doctrine of Non-Interference” in Technical Evaluation: Courts consistently refuse to sit in appeal over the technical evaluations of expert committees of government agencies, unless there is a glaring illegality. This respects the autonomy of administrative decision-making.
V. Critical Analysis and Potential Challenges
While the intent behind this judicial restriction is laudable and addresses a genuine developmental need, it raises important questions:
» Risk of Arbitrariness Going Unchecked: Could this hands-off approach embolden state authorities to act arbitrarily, knowing judicial recourse is difficult? The judiciary maintains the “mala fides and arbitrariness” exception, but the high threshold may deter legitimate challenges.
» The Small Contractor’s Plight: A small or medium enterprise wrongfully excluded or terminated may lack the financial stamina to fight a long-drawn damages claim. An injunction was sometimes its only leverage. The new regime may disproportionately disadvantage smaller players.
» Quality vs. Speed: By prioritizing speed and non-interference, is there a risk of overlooking serious concerns about corruption, safety compromises, or environmental violations raised by citizens or NGOs? The courts must carefully carve out exceptions for cases involving fundamental rights, fraud, or grave illegality.
» Implementation by Lower Courts: The Supreme Court’s clear doctrine often faces inconsistent application in District Courts and some High Courts. The cultural shift from an interventionist to a restrictive mindset is a work in progress across the judicial hierarchy.
Conclusion
The trajectory of Indian jurisprudence concerning public works contracts and specific relief is unmistakably toward severe judicial restriction on interference. This is a deliberate, policy-driven shift where the judiciary has reinterpreted ancient principles of equity through the lens of contemporary economic and public necessity. The amended Specific Relief Act, 2018, provided the statutory scaffold, but it is the Supreme Court’s robust and consistent interpretation that has breathed life into it, creating a formidable legal barrier against project-delaying litigation.
The courts have effectively rewritten the playbook: “public interest” is the paramount consideration; “balance of convenience” almost invariably favours project continuation; “irreparable injury” is rarely found on the contractor’s side; and specific performance is an illusory remedy for large works. This recalibration seeks to transform India’s infrastructure ecosystem—from one plagued by legal entanglements to one where projects move forward with legal certainty and speed.
The ultimate aim is to alter the strategic calculus of disputing parties, steering them away from interim battles and towards expedited final resolution or damages. While the approach demands vigilance to prevent its misuse as a shield for arbitrary state action, its core philosophy—that the collective good of timely infrastructure delivery must trump individual contractual disputes—represents a significant and necessary evolution in Indian contract law. The judiciary has signaled that it is no longer a passive adjudicator but an active stakeholder in nation-building, clearing the legal tracks for the express train of development. The challenge ahead lies in ensuring that this powerful doctrine of restraint is applied with nuance, preserving access to justice for legitimate grievances while steadfastly protecting the public’s right to the fruits of progress.
Here are some questions and answers on the topic:
Question 1: What is the fundamental shift in judicial attitude towards granting injunctions in public works contracts after the 2018 amendment to the Specific Relief Act, and how has this been operationalized by the courts?
Answer: The fundamental shift is from a discretionary, equity-based approach to a rule-based, public-interest-centric doctrine of judicial restraint. Prior to the amendment, courts often granted injunctions to maintain the status quo based on a prima facie case, balance of convenience, and irreparable injury, which frequently led to the stalling of infrastructure projects. The Specific Relief (Amendment) Act, 2018, particularly through Section 20A, introduced a statutory presumption against injunctions if they would cause delay or impediment to an infrastructure project. The judiciary, led by the Supreme Court, has operationalized this by imposing a significantly higher burden of proof. Now, a plaintiff must demonstrate not just a prima facie case but a "strong prima facie case" that the injunction will not hinder the project. The courts have radically reinterpreted the "balance of convenience" to be almost automatically in favour of allowing the project to proceed, arguing that the public injury from delay—economic loss, missed developmental goals, and cost escalation—is incalculable and outweighs any private, compensable injury to a contractor. This operational shift means that merely raising a triable issue or alleging a procedural irregularity is insufficient to obtain an injunction; the claim must be compelling and clear at the very threshold.
Question 2: How have the courts redefined the classic principles of "balance of convenience" and "irreparable injury" in the context of public infrastructure disputes?
Answer: The courts have fundamentally redefined these principles by placing the "public interest" at their core. The "balance of convenience" is no longer a neutral weighing of hardships between the two parties to the suit. In public works disputes, it is now a near-irrebuttable presumption that the balance tilts decisively against granting any injunction. The inconvenience to the public from a stalled project—commuters without transport, patients without a hospital, economic losses from delayed infrastructure—is deemed colossal and perpetual. In contrast, the inconvenience to an aggrieved contractor or bidder is considered finite, monetary, and capable of being remedied through damages or a later claim. Similarly, "irreparable injury" has been redefined. A contractor claiming wrongful termination cannot typically satisfy this condition because their injury is viewed as "reparable" by money. The courts hold that the availability of damages as an adequate remedy negates the claim of irreparable harm. Conversely, the injury to the state and the public from a delayed project—the loss of time, the escalation of costs, and the deprivation of a public asset—is seen as truly irreparable, as no damages award can restore the lost time or the opportunity cost to society.
Question 3: What is the judicial reasoning behind the growing reluctance to grant the remedy of specific performance for large public works and infrastructure contracts?
Answer: The judicial reasoning is twofold, primarily anchored in the amended Section 14(1)(e) of the Specific Relief Act. First, courts assert that large infrastructure and construction contracts are inherently "personal" in nature. They depend on the specific skills, expertise, management, and continuous mutual trust and confidence between the contracting agency and the contractor. When this relationship sours, often leading to termination, the courts deem it imprudent and impractical to force a "marriage" between unwilling parties through a decree of specific performance. Second, and critically, such contracts involve "continuous supervision" of complex, technical, and long-duration work. The judiciary has consistently held that it is ill-equipped and lacks the institutional capacity to supervise the day-to-day execution of building a highway, power plant, or metro line. Granting specific performance would require the court to micromanage technical decisions, quality control, and scheduling, a role it is unwilling and unable to assume. Therefore, the judiciary consciously relegates the aggrieved party to a claim for damages, viewing this as a more efficient and appropriate solution that allows the public authority to swiftly engage a new agency to complete the project for the public good.
Question 4: Beyond the Specific Relief Act, what general judicial doctrines has the Supreme Court emphasized to create a "no-stay" culture for high-value public utility projects?
Answer: Beyond the statutory confines of the Specific Relief Act, the Supreme Court has issued a series of overarching judicial directives to ingrain a "no-stay" culture across the entire judiciary. In landmark orders like Assistant Commissioner (CT) vs. M/s. Satyam Shivam Papers Ltd., the Court has laid down a general principle that high-value public utility and revenue-generating projects must not be stalled by interim orders. It has directed all High Courts to ensure that such projects are not stayed without recording compelling and exceptional reasons. The Court mandates that any order granting a stay must explicitly analyze and justify how the balance of convenience favours the stay, considering the massive public detriment and national loss from delay. This creates a blanket doctrine of restraint that applies even in writ jurisdictions, tax matters, or other civil suits that indirectly impact project progress. The Supreme Court has essentially issued a judicial policy that the default position is non-interference, and any deviation requires a heavy, reasoned burden to be discharged by the party seeking the stay, thereby institutionalizing caution and restraint at all levels of the judiciary.
Question 5: What are the potential criticisms or challenges associated with this robust judicial policy of non-interference in public works contracts?
Answer: While the policy is driven by laudable developmental goals, it faces significant criticisms and challenges. The primary concern is that it may create an imbalance of power, potentially shielding state authorities from legitimate scrutiny. The exceptionally high bar for proving mala fides or arbitrariness might deter genuine challenges against corrupt or patently illegal actions by government agencies, allowing such actions to proceed unchecked until project completion. Secondly, it may disproportionately affect small and medium enterprises (SMEs). For an SME contractor, an injunction was often a critical tool for survival and leverage; being relegated to a long-drawn damages claim can be a death knell due to financial and temporal constraints. Thirdly, there is a risk that the singular focus on speed could marginalize other vital public interests, such as environmental compliance, procedural fairness, and quality and safety standards. Courts must carefully carve out exceptions where fundamental rights, fraud, or grave statutory violations are involved. Finally, the consistent application of this doctrine remains a challenge. The Supreme Court's clear philosophy often meets with uneven understanding and application in various High Courts and District Courts, where older, more interventionist habits may persist, indicating that the cultural shift in the judicial mindset is still a work in progress across the entire legal system.
Disclaimer: The content shared in this blog is intended solely for general informational and educational purposes. It provides only a basic understanding of the subject and should not be considered as professional legal advice. For specific guidance or in-depth legal assistance, readers are strongly advised to consult a qualified legal professional.



Comments