“Role Of Judicial Intervention (E.g. Stay / Setting Aside) In Arbitration Recent Sc / HC Decisions”
- Lawcurb

- Nov 4
- 14 min read
Abstract
The Indian arbitration landscape has undergone a seismic shift, moving from a regime of extensive judicial intervention to one that fervently espouses the principle of minimal interference. This transformation, spearheaded by the Arbitration and Conciliation (Amendment) Act, 2015, and subsequent amendments in 2019 and 2021, was aimed at aligning Indian arbitration law with the global pro-arbitration ethos and establishing India as an international arbitration hub. The core of this conflict lies at two critical junctures: the stage of seeking a stay on court proceedings in favor of arbitration (Section 8) and challenging an arbitral award (Section 34). This article provides a detailed analysis of the evolving role of the Indian judiciary, particularly the Supreme Court and various High Courts, in interpreting and applying these provisions. It traces the jurisprudential journey from the interventionist approach in ONGC v. Saw Pipes to the restrictive paradigm ushered in by amendments and fortified by landmark decisions like Ssangyong Engineering & Construction Co. Ltd. v. NHAI and Dakshin Haryana Bijli Vitran Nigam Ltd. v. M/s Navigant Technologies Pvt. Ltd.. The article critically examines the "patent illegality" ground, the contours of "public policy," and the "unconditional stay" provision, arguing that while the judiciary has largely embraced a pro-arbitration stance, nuanced challenges remain in ensuring that this minimal intervention does not come at the cost of substantive justice and fundamental legal principles.
1. Introduction
Arbitration, as an alternative dispute resolution (ADR) mechanism, is founded on the cornerstone principles of party autonomy, speed, and finality. Its efficacy, however, is invariably linked to the extent of supervisory jurisdiction exercised by national courts. Excessive judicial intervention can strangle the very purpose of arbitration, rendering it a mere preliminary step to protracted litigation. Conversely, a complete hands-off approach could lead to arbitral tyranny, where awards suffering from fundamental flaws are enforced.
In India, the Arbitration and Conciliation Act, 1996 ("the Act"), was enacted to consolidate and amend the law relating to domestic and international arbitration, and to define the law relating to conciliation. Modeled on the UNCITRAL Model Law on International Commercial Arbitration (1985), its objective was to minimize the role of courts in the arbitral process. However, for the first two decades, judicial interpretation, particularly by the Supreme Court, often widened the scope of intervention, most notably through the expansive interpretation of "public policy of India" as a ground for setting aside an arbitral award under Section 34.
Recognizing that this judicial expansionism was defeating the object of the Act, the Indian legislature embarked on a reformative journey. The Arbitration and Conciliation (Amendment) Act, 2015, was a watershed moment, aimed at reducing judicial intervention and expediting the arbitration process. This was further refined by the 2019 and 2021 Amendments. The judiciary, in turn, has responded to this legislative intent with a series of landmark judgments that have significantly curtailed its own power to interfere with arbitral awards.
This article delves into the heart of this dynamic interplay between legislative reform and judicial interpretation. It is structured to first establish the statutory framework governing judicial intervention, specifically through the mechanisms of staying court proceedings (Section 8) and setting aside arbitral awards (Section 34). The core of the article is a detailed analysis of recent judicial pronouncements that have redefined the boundaries of this intervention. It will explore the paradigm shift in the approach to public policy and patent illegality, the strict conditions for referring parties to arbitration, and the emerging nuances that continue to challenge the courts. The objective is to provide a comprehensive understanding of how the Indian judiciary is currently walking the tightrope between respecting party autonomy and upholding the foundational principles of justice.
2. The Statutory Framework for Judicial Intervention
The Act provides specific, limited gateways through which the Indian judiciary can intervene in the arbitral process. The two most critical stages for such intervention are at the threshold (seeking a reference to arbitration) and at the terminus (challenging the final award).
2.1. Intervention at the Threshold: Section 8 - Reference to Arbitration
Section 8 of the Act mandates a judicial authority before which an action is brought in a matter which is the subject of an arbitration agreement, to refer the parties to arbitration, if a party so applies not later than the date of submitting his first statement on the substance of the dispute.
The pre-2015 position was somewhat diluted by judicial interpretations that allowed courts to examine aspects like the validity and existence of the arbitration agreement at this preliminary stage. The 2015 Amendment sought to remedy this by making the reference virtually automatic upon the satisfaction of the following conditions:
• An arbitration agreement exists.
• A party to the agreement brings an action in court against the other party.
• The subject matter of the action is the same as the subject matter of the arbitration agreement.
• The other party applies for reference before submitting its first statement on the substance of the dispute.
The amendment significantly curtailed the court's ability to delve into the merits of the case or conduct a detailed examination of the arbitration agreement's validity at this stage.
2.2. Intervention at the Terminus: Section 34 - Setting Aside the Arbitral Award
This is the most significant provision for judicial intervention. An arbitral award can be set aside only on the grounds explicitly enumerated in Section 34. The 1996 Act originally contained grounds largely mirroring Article 34 of the UNCITRAL Model Law, but Indian judicial interpretation, particularly the decision in ONGC v. Saw Pipes Ltd. (2003), added a vast and unpredictable ground by holding that an award could be set aside if it was "patently illegal" or contrary to "the public policy of India." This was interpreted to include errors of fact or law apparent on the face of the award, effectively turning a setting aside proceeding into an appellate proceeding.
The 2015 Amendment was a direct response to this. It sought to narrow the scope of "public policy" by adding an Explanation to Section 34(2)(b)(ii), clarifying that an award conflicts with the public policy of India only if it:
(i) was induced by fraud or corruption, or
(ii) is in contravention with the fundamental policy of Indian law, or
(iii) conflicts with the most basic notions of morality or justice.
Most importantly, the amendment explicitly stated that "the test as to whether there is a contravention with the fundamental policy of Indian law shall not entail a review on the merits of the dispute."
A new ground, Section 34(2A), was introduced for domestic arbitrations, allowing setting aside on the ground of "patent illegality appearing on the face of the award," while again cautioning that this "shall not entail a review on the merits of the dispute."
3. The Paradigm Shift: A Pro-Arbitration Judiciary in Action
The legislative intent of the 2015 Amendment has been wholeheartedly embraced and vigorously enforced by the Supreme Court in a line of landmark judgments.
3.1. The New Lodestar: Ssangyong Engineering & Construction Co. Ltd. v. NHAI (2019)
This case is arguably the most important post-amendment judgment on the scope of judicial intervention under Section 34. The Supreme Court, interpreting the amended provisions, laid down several crucial principles:
» Narrowing 'Public Policy': The Court unequivocally held that the ground of "public policy" is now constricted to the three categories mentioned in the Explanation. It overruled the wider interpretations that had developed post-Saw Pipes.
» 'Fundamental Policy of Indian Law': The Court explained that this refers to the core, foundational principles of Indian law. A contravention of a substantive law per se would not qualify unless it is a violation of a principle that constitutes the fundamental policy of Indian law. Examples include compliance with the principles of natural justice (audi alteram partem), the doctrine of judicial review, and the principle that a court or tribunal must act bona fide.
» No Re-appreciation of Evidence: The Court repeatedly emphasized that a court hearing a Section 34 petition cannot sit as a court of appeal and re-appreciate the evidence. The arbitrator is the sole judge of the quality and quantity of evidence, and it is not for the court to substitute its own view.
» Patent Illegality (Section 34(2A)): The Court clarified that "patent illegality" must be one that goes to the root of the matter and cannot be of a trivial nature. An erroneous application of law or re-appreciation of evidence is not permitted. An award could be patently illegal if, for instance, the arbitrator has given no reasons in a case where reasoning is required, or has ignored the terms of the contract between the parties.
The Ssangyong judgment signaled a clear and decisive break from the past, instructing courts to exercise extreme restraint and to interfere only in the rarest of cases where the award suffers from a fundamental flaw, not merely an erroneous finding.
3.2. Reinforcing Restraint: Dakshin Haryana Bijli Vitran Nigam Ltd. v. M/s Navigant Technologies Pvt. Ltd. (2021)
Following Ssangyong, the Supreme Court in Dakshin Haryana further tightened the noose around judicial intervention. The Court held:
» Limited Scope of 'Patent Illegality': It stated that a court cannot interfere with an award merely because, in its view, the arbitrator has arrived at a wrong conclusion. The "patent illegality" ground is not a backdoor for appealing against the award.
» Respect for Arbitrator's Interpretation: The Court affirmed that if an arbitrator adopts a possible and plausible view, even if the court thinks another view is more compelling, the award must stand. The arbitrator's interpretation of the contract is final and binding, unless it is so perverse that no reasonable person could have arrived at it.
This judgment served as a stern reminder to litigants, particularly state-owned entities accustomed to challenging unfavorable awards, that the courts would no longer entertain disguised appeals under the garb of Section 34 petitions.
3.3. The "Unconditional Stay" Conundrium: Section 36 Amendment
Section 36 of the Act deals with the enforcement of awards. Pre-2015, the filing of a Section 34 petition automatically stayed the execution of the award, allowing recalcitrant parties to delay payment indefinitely.
The 2015 Amendment changed this, providing that the mere filing of a setting aside application would not operate as an automatic stay. The award debtor had to file a separate application for stay, and the court could grant it subject to conditions, typically a direction to deposit the entire award amount or a substantial part of it.
However, the 2019 Amendment introduced a proviso to Section 36(3), which states that where the court is satisfied that the arbitration agreement or contract underlying the award is "induced by fraud or corruption", it shall grant an unconditional stay on the execution of the award.
» Recent HC Interpretation: This provision has raised concerns about potentially opening a new avenue for delay. However, High Courts have begun interpreting it strictly. For instance, the Delhi High Court in Punj Lloyd Ltd. v. Oil & Natural Gas Corporation Ltd. (2023) held that the unconditional stay is not automatic. The court must be prima facie satisfied based on evidence that the arbitration agreement or the contract itself was vitiated by fraud or corruption. Allegations of fraud in the performance of the contract would not suffice. This interpretation ensures that this provision is not misused by award debtors to simply avoid payment by making bald allegations of fraud.
4. Nuanced Challenges and Evolving Jurisprudence
Despite the clear pro-arbitration stance, courts continue to grapple with nuanced situations that test the boundaries of minimal intervention.
4.1. The Non-Arbitrability of Disputes
Certain categories of disputes are considered non-arbitrable as they involve rights in rem or are reserved for the exclusive domain of public fora. The Supreme Court in Vidya Drolia v. Durga Trading Corporation (2021) laid down a four-fold test to determine non-arbitrability, but ultimately reinforced the "pro-arbitration" lean by holding that when in doubt, the court should refer the parties to arbitration. Disputes relating to fraud, though complex, are generally arbitrable unless the fraud is of such a nature that it vitiates the entire contract, including the arbitration clause.
4.2. Contravention of the Terms of the Contract
A recurring issue is whether an arbitrator's decision that allegedly contradicts the express terms of the contract can be set aside. The consistent judicial view post-amendment is that an arbitrator is the final arbiter of the contract. The Supreme Court in PSA SICAL Terminals Pvt. Ltd. v. Board of Trustees of V.O. Chidambranar Port Trust (2021) held that if the arbitrator's interpretation of the contract is a possible one, even if the court believes it to be incorrect, it is not a ground for interference. Interference is warranted only if the arbitrator rewrites the contract, creating a new agreement for the parties.
4.3. Group of Companies Doctrine
The "group of companies" doctrine, which allows non-signatory affiliates to be bound by or allowed to invoke an arbitration agreement, has received recent judicial affirmation. The Supreme Court in Cox and Kings Ltd. v. SAP India Pvt. Ltd. (2023) reaffirmed the application of this doctrine in Indian arbitration law, emphasizing that the intention of the parties is the central theme. This demonstrates the court's willingness to look beyond strict privity of contract to give effect to the commercial reality and the parties' true intent, thereby promoting arbitration.
4.4. International Commercial Arbitration
In the realm of international commercial arbitration seated in India, the grounds for setting aside under Section 34 are even more restricted. The ground of "patent illegality" under Section 34(2A) is not available for challenging international commercial arbitral awards. This creates a dual standard, providing greater finality to international awards and reinforcing India's commitment to international best practices.
5. Conclusion: A Journey Towards Finality with Caution
The trajectory of judicial intervention in Indian arbitration is a compelling narrative of course correction. From the expansive and unpredictable era of Saw Pipes, the Indian legal system has consciously and deliberately moved towards a regime that prioritizes party autonomy and the finality of arbitral awards. The 2015 and subsequent amendments provided the legislative toolkit, and the Supreme Court, through its landmark decisions in Ssangyong, Dakshin Haryana, and others, has emerged as a steadfast guardian of this pro-arbitration policy.
The role of judicial intervention today is not to re-adjudicate disputes but to act as a safety valve—a mechanism of last resort to correct only those awards that are vitiated by fundamental breaches of justice, fraud, or a patent illegality that strikes at the very root of the arbitral process. The message to courts is clear: respect the arbitrator's mandate, do not re-appreciate evidence, and uphold awards unless they shock the judicial conscience.
However, this journey is not without its challenges. The introduction of the "unconditional stay" provision for fraud requires careful judicial scrutiny to prevent its misuse. Similarly, the distinction between a possible view and a perverse one can sometimes be a thin line, requiring judges to exercise sophisticated discretion.
In conclusion, the Indian judiciary has successfully walked the tightrope, striking a commendable balance between minimal intervention and the need to preserve the integrity of the arbitral process. While the path to becoming a global arbitration hub is long, the foundational principles of speed, cost-effectiveness, and finality are now firmly supported by a robust and progressive jurisprudential framework. The continued success of this project will depend on the consistent application of these restrictive principles by courts at all levels, ensuring that arbitration in India truly becomes an alternative to litigation, and not a precursor to it.
Here are some questions and answers on the topic:
1. What was the fundamental shift brought about by the 2015 Amendment to the Arbitration Act regarding the ground of "public policy" for setting aside an award, and how did the Supreme Court reinforce this change?
The 2015 Amendment was a legislative correction to the widely interpreted "public policy" ground established by the Supreme Court in the ONGC v. Saw Pipes case. Prior to the amendment, an award could be set aside if it was patently illegal or contrary to the interests of India, which allowed courts to re-examine the merits of the dispute under the guise of public policy. The 2015 Amendment drastically narrowed this scope by adding an Explanation to Section 34, clarifying that an award conflicts with public policy only if it was induced by fraud or corruption, violates the fundamental policy of Indian law, or conflicts with the most basic notions of morality or justice. The Supreme Court, in the landmark case of Ssangyong Engineering & Construction Co. Ltd. v. NHAI (2019), wholeheartedly embraced this legislative intent. It explicitly held that the ground of public policy is now constricted to these three categories and firmly stated that a review on the merits of the dispute is impermissible. This judgment signaled a decisive break from the past, instructing courts to exercise extreme restraint and to interfere only in rarest of cases where a fundamental flaw, and not a mere error, is present in the award.
2. How has the Supreme Court defined and limited the scope of the "patent illegality" ground for setting aside a domestic arbitral award after the 2015 amendments?
The "patent illegality" ground, introduced under Section 34(2A) for domestic awards, has been interpreted by the Supreme Court in a very restrictive manner to prevent it from becoming a backdoor appeal. In the Ssangyong case, the Court clarified that an award is patently illegal only if the illegality goes to the root of the matter and is not trivial. It does not cover an erroneous application of the law or a re-appreciation of evidence. This principle was powerfully reinforced in Dakshin Haryana Bijli Vitran Nigam Ltd. v. M/s Navigant Technologies Pvt. Ltd. (2021). The Court in this case held that a court cannot interfere with an award merely because, in its view, the arbitrator has arrived at a wrong conclusion. It affirmed that if an arbitrator adopts a possible and plausible view of the facts or the contract, the award must stand, even if the court believes another view is more compelling. Interference is warranted only if the interpretation is so perverse that no reasonable person could have arrived at it, or if the arbitrator has ignored the explicit terms of the contract.
3. What is the significance of the change from an "automatic stay" to a "conditional stay" on the enforcement of an arbitral award, and what is the exception introduced in 2019?
Prior to the 2015 Amendment, the mere filing of a petition to set aside an arbitral award automatically stayed its enforcement, allowing a losing party to delay payment indefinitely. The 2015 Amendment was a crucial reform that removed this automatic stay. It mandated that filing a challenge under Section 34 would not by itself stop enforcement; the award debtor had to file a separate application for a stay, which the court could grant subject to conditions, often requiring the debtor to deposit the entire award amount or a substantial part as security. This ensured that successful award claimants were not deprived of the fruits of their victory during lengthy court challenges. However, the 2019 Amendment introduced a significant exception. It added a proviso that if the court is prima facie satisfied that the arbitration agreement or the underlying contract was "induced by fraud or corruption," it shall grant an unconditional stay on the award's execution. High Courts, like the Delhi High Court in Punj Lloyd Ltd. v. ONGC (2023), have since interpreted this exception strictly, requiring concrete evidence of fraud that vitiates the contract itself, not just allegations of fraudulent performance, to prevent misuse of this provision.
4. How do the courts now approach a situation where an arbitral award is challenged on the basis that the arbitrator misinterpreted the contract between the parties?
The consistent judicial approach post the 2015 amendments has been to respect the arbitrator's authority as the final interpreter of the contract. The Supreme Court has repeatedly held that a court acting under Section 34 cannot act as an appellate authority and substitute its own interpretation for that of the arbitrator. In the case of PSA SICAL Terminals Pvt. Ltd. v. Board of Trustees of V.O. Chidambranar Port Trust (2021), the Court reinforced that an arbitral tribunal must adhere to the contract, but if its interpretation of the contractual terms is a possible or plausible one, even if the court believes it to be incorrect, it is not a ground for setting aside the award. The judiciary's role is not to ensure that the arbitrator has arrived at the "correct" interpretation, but to ensure that the interpretation is not so perverse or irrational that it effectively rewrites the contract for the parties. Interference is justified only when the arbitrator travels beyond the scope of the contract and creates a new agreement.
5. In what way has the Supreme Court's approach to referring parties to arbitration under Section 8 evolved to minimize judicial intervention at the preliminary stage?
The Supreme Court has significantly streamlined the process under Section 8 to ensure that parties are referred to arbitration with minimal judicial scrutiny at the threshold. The pre-2015 position allowed courts to examine the validity and existence of the arbitration agreement in detail at this stage, which often led to delays. The 2015 Amendment tightened the language of Section 8, making the reference to arbitration virtually automatic and mandatory if a valid arbitration agreement exists and the application is made in a timely manner. The Supreme Court, in cases like Vidya Drolia v. Durga Trading Corporation (2021), has reinforced this pro-arbitration stance. The Court laid down a test for non-arbitrability but ultimately held that when there is even a slight doubt regarding the existence of a valid arbitration agreement or the arbitrability of the dispute, the matter should be referred to the arbitral tribunal for a decision. This approach, known as the "competence-competence" principle, defers substantive issues to the tribunal itself, thereby reducing preliminary litigation and ensuring that the arbitral process commences without unnecessary judicial obstruction.
Disclaimer: The content shared in this blog is intended solely for general informational and educational purposes. It provides only a basic understanding of the subject and should not be considered as professional legal advice. For specific guidance or in-depth legal assistance, readers are strongly advised to consult a qualified legal professional.